RECENT PROJECTS
BMI Murarrie
Brookfield
Bunnings Warehouse
Causeway Upgrades
Dalby Ergon Energy
Halcyon
Jimbelunga
Kerrisdale Gardens Stage 1
Logan City Golf
Loganhome State School
Nudgee Road
Police Driver Centre
UQ Long Pocket
VGL-Warehouse
PAST PROJECTS
STAGE 1 – CURLEW STREET, PORT OF BRISBANE
CLIENT
Port of Brisbane/Platinum Projects
YEAR
March 2012
DESCRIPTION
Installation of sewer, 300 mm DICL water main with SV and hydrants plus 350mm to 1500 diameter stormwater. This project included building all the manholes and access chambers.
STAGE 2 – CNR BISHOP AND LUCINDA DRIVE, PORT OF BRISBANE
CLIENT
Port of Brisbane/Platinum Projects
YEAR
December 2012
DESCRIPTION
Installation of sewer, 300 mm DICL water main with SV and hydrants plus 350 mm to 1800 diameter stormwater. This project included building all the manholes and access chambers plus the base slab for the large box culverts.
RADAR STREET, LYTTON
CLIENT
Port of Brisbane/Platinum Projects
YEAR
January 2012
DESCRIPTION
Installation of sewer, 150 mm DICL main with SV and hydrants plus 350 mm to 1800 diameter stormwater. This project included building all the manholes and access chambers plus the base slab for the large box culverts.
NORTHERN BEACHES STATE HIGH SCHOOL
CLIENT
Paynter Dixon
YEAR
December 2012
DESCRIPTION
This project included installing over a thousand lengths of pipe of storm water and sewer pipe, construction of manholes, RCBC in situ bases, sewer manholes. The pipe ranged from 150 mm sewer to 900 stormwater.
WHIMBREL STREET, PORT OF BRISBANE
CLIENT
Port of Brisbane/Platinum Projects
YEAR
July 2013
DESCRIPTION
Installation of twin 1500 stormwater line and associated manholes structures plus the installation of a 40T plus GPT unit. This project had its difficulties for completion due to the new line being constructed in a live drain, as well as inclement, rainy weather that resulted at times with two foot of water running through the job site. The project, however, was completed successfully due to the skills and experience of Civcorp staff.
Q100 CHANNEL, PORT OF BRISBANE
CLIENT
Port of Brisbane/Platinum Projects
YEAR
November 2013
DESCRIPTION
With this project Civcorp built a grout-filled mattress channel that covered an area of around 16,000m2; this channel was designed to take the stormwater from current and future buildings and pavements. This work included a twin 1800 mm line and rock outlet into Moreton Bay.
T12 STORMWATER
CLIENT
Port of Brisbane/Platinum Projects
YEAR
May 2014
DESCRIPTION
Installation of 450 lengths of 1500 stormwater pipe plus 8 access chambers.
GAYNDAH POLE DEPOT
CLIENT
Ergon Energy
YEAR
May 2014
DESCRIPTION
Concrete hard stand.
LOGANHOLME WWTP
CLIENT
Tennix/Logan Water Alliance
YEAR
June 2014
DESCRIPTION
Roadworks.